| The main motor equipment of Zhulinhu Pumping Station Project of Dujiatai Flood Separation and Storage Area of Hubei Province (Wuhan Section) has passed acceptance
2023-08-23
On August 21, 2023, Wuhan Bilshui Group Co., Ltd. organized a factory acceptance meeting for the main motor equipment (4 sets of TL2500-48/4500 10Kv vertical synchronous motors) of Zhulinhu Pumping Station, EPC general contract project of Dujiatai flood Storage and safety Construction Project (Wuhan section) in our company. The participants mainly included Wuhan Water Conservancy Bureau, the project authority, Sichuan Yuanfeng Construction Project Management Co., LTD., the supervision unit, Hubei Water Conservancy and Hydropower Planning Survey and Design Institute Co., LTD., the design unit, Hubei Haochuan Water Conservancy and Hydropower Engineering Co., LTD., the construction unit, and Wuhan Bishui Investment and Operation Co., LTD. The participants reviewed and listened to the factory acceptance data and related reports of the first motor of our company, and witnessed the factory test of the motor. After full discussion and review, the experts of the acceptance group gave a high degree of affirmation to the performance indicators and stability of the motor, and unanimously agreed to pass the factory acceptance.